One data center project pulled and another delayed in Hanover, as supervisors reinstitute equipment tax
News ClipRichmond BizSense·Hanover County, VA

One data center project pulled and another delayed in Hanover, as supervisors reinstitute equipment tax

LS Power withdrew a data center project zoning request in Hanover County, Virginia, while a vote on WestDulles Properties' Iron Horse project was delayed. Concurrently, the Hanover Board of Supervisors reinstated the county's previous data center equipment tax rate. Another project by Tract was recently denied by the supervisors.

6/26/2026
Hanover Planning Commission to Vote on Data Center Project Near Ashland
News ClipRichmond BizSense·Ashland, Hanover County, VA

Hanover Planning Commission to Vote on Data Center Project Near Ashland

The Hanover Planning Commission is scheduled to vote on a zoning request for WestDulles Properties' proposed Iron Horse data center project near Ashland. This 180-acre campus is envisioned to include up to nine data center buildings and follows a previous rejection by county supervisors.

6/15/2026
HHHunt comes back with 98-home plan for site near Wyndham previously pitched for data centers
News ClipRichmond BizSense·Hanover County, VA

HHHunt comes back with 98-home plan for site near Wyndham previously pitched for data centers

HHHunt's proposal for a data center campus in Hanover County, Virginia, was rejected by the Planning Commission following resident opposition, leading the company to withdraw its plans. HHHunt has now submitted a third, smaller residential development plan for the site. Other data center projects in Hanover County are also facing regulatory scrutiny.

6/12/2026
Zoning appeals board rejects challenge to permit requirement for data center project in Chester
News ClipRichmond BizSense·Chester, Chesterfield County, VA

Zoning appeals board rejects challenge to permit requirement for data center project in Chester

The Chesterfield Board of Zoning Appeals rejected an appeal challenging the requirement for a conditional-use permit for a data center project in Chester. The landowner argued they had vested rights under a previous ordinance, but the board upheld the county's determination that a CUP is now required. This decision means the project must now apply for a conditional-use permit to proceed.

6/4/2026
Latest Iron Horse data center proposal teed up for Hanover Planning Commission review
News ClipRichmond BizSense·Ashland, Hanover County, VA

Latest Iron Horse data center proposal teed up for Hanover Planning Commission review

WestDulles Properties is bringing an amended Iron Horse data center proposal before the Hanover Planning Commission in Virginia. This new plan, which includes less buildable area and lower height restrictions, aims to address concerns that led to a previous rejection by the Hanover Board of Supervisors. The project straddles the Hanover-Ashland line, with the Ashland portion already approved.

5/14/2026
Developer appealing permit requirement for data center project in Chesterfield
News ClipRichmond BizSense·Chesterfield County, VA

Developer appealing permit requirement for data center project in Chesterfield

A developer in Chesterfield, Virginia is appealing a county planning department ruling that a proposed data center project requires a conditional-use permit to proceed. The developer claims the project should be grandfathered under the previous zoning ordinance which allowed data centers as a by-right use in the industrial zoning district. The matter will be heard by the Chesterfield Board of Zoning Appeals in May.