Oracle says Project Jupiter could turn to grid power if air permit falls through
Oracle informed Doña Ana County commissioners that its Project Jupiter data center may need to connect to the existing power grid if its planned on-site fuel-cell system fails to secure an air quality permit. This potential change could require amendments to the project's existing agreements. The company emphasized its commitment to the off-grid plan while detailing the fuel cell's environmental benefits and progress on construction and employment.