Worldwide Mission Critical

Data Center Signal is tracking 6 clips about Worldwide Mission Critical data center developments across 1 states, including NE.

Loading...
6Clips
1States

States

Topics

electricity100%
government100%
zoning100%
water83%
environmental83%
announcement50%
opposition33%
moratorium17%
Data center project gets approval from Kearney city council, with new stricter regulations
News ClipCentral Nebraska Today·Kearney, Buffalo County, NE

Data center project gets approval from Kearney city council, with new stricter regulations

The Kearney City Council approved a conditional use permit for a new data center project, Project Horizon, from Worldwide Mission Critical, SDV, and MARA. The approval came with new stricter regulations addressing concerns about sound and water usage, despite opposition from some local residents. The project is expected to begin construction in late 2024 and operate by 2028.

9/9/2026
368-megawatt AI data center approved in Kearney
News Clipjournalstar.com·Kearney, Buffalo County, NE

368-megawatt AI data center approved in Kearney$

The Kearney City Council approved the Tech One Crossing AI data center project, developed by Worldwide Mission Critical. This approval followed the adoption of revised data center regulations and the rezoning of the project site. The new facility will consume 368 megawatts of energy and replaces an existing cryptocurrency mine.

9/9/2026
Data center conditional use permit to be discussed by Kearney city council tonight
News ClipCentral Nebraska Today·Kearney, Buffalo County, NE

Data center conditional use permit to be discussed by Kearney city council tonight

The Kearney City Council is set to discuss a conditional use permit for a 368 megawatt data center proposed by Worldwide Mission Critical. The council will also review proposed new regulations for data centers, which include extensive requirements for setbacks, noise, and utility infrastructure. The Planning Commission has already unanimously recommended approval of the data center's conditional use permit.

9/8/2026
Kearney poised to go all in on data centers even as many Nebraska towns throttle back
News ClipFlatwater Free Press·Kearney, Buffalo County, NE

Kearney poised to go all in on data centers even as many Nebraska towns throttle back

The city of Kearney, Nebraska, is moving forward with a major 368-megawatt data center campus, Tech One Crossing, by Worldwide Mission Critical, after adopting a new zoning ordinance with specific restrictions. This initiative contrasts with a trend of moratoriums in other Nebraska communities. The project still requires final approval from the Kearney City Council, amidst resident concerns over noise, water, and energy use.

9/8/2026
Data center project receives nod from Kearney Planning Commission with new regulations in place
News ClipCentral Nebraska Today·Kearney, Buffalo County, NE

Data center project receives nod from Kearney Planning Commission with new regulations in place

The Kearney Planning Commission has approved a conditional use permit for the "Project Horizon" data center, proposed by Worldwide Mission Critical and SDV, to be located east of Kearney. The approval includes new stricter regulations, with the project slated for a City Council review on September 8th. Community members expressed concerns regarding sound and water usage.

8/21/2026
Data center conditional use permit to be discussed at Kearney Planning Commission meeting
News ClipCentral Nebraska Today·Kearney, Buffalo County, NE

Data center conditional use permit to be discussed at Kearney Planning Commission meeting

The Kearney Planning Commission is set to discuss a conditional use permit for a new data center proposed by Worldwide Mission Critical, located east of Kearney. The facility plans for a total electrical demand of 368 megawatts and will utilize closed-loop chilled water systems. City staff are recommending approval of the permit with several conditions.

8/18/2026