Spartanburg County Council approves preliminary NorthMark data center development agreement
News ClipPost and Courier·Spartanburg County, SC

Spartanburg County Council approves preliminary NorthMark data center development agreement$

Spartanburg County Council approved a preliminary development agreement for the NorthMark and Valara data center under the county’s data center moratorium. The agreement requires reporting and compliance measures covering noise, light, landscaping, water, utility demand and air quality, while allowing accelerated approval reviews.

10/23/2026
Data center ordinance in Spartanburg County passes first reading
News Clip1:13FOX Carolina News·Spartanburg County, SC

Data center ordinance in Spartanburg County passes first reading

Spartanburg County leaders gave a first reading to a development agreement for the Valara data center under construction along South Pine Street outside Spartanburg city limits. The proposed agreement would expand county oversight to air, water, noise and lighting impacts, while a previously approved one-year pause on new data centers remains in effect.

10/23/2026
Spartanburg County Council asks state for east side air quality monitoring station
News ClipPost and Courier·Spartanburg County, SC

Spartanburg County Council asks state for east side air quality monitoring station$

The Spartanburg County Council passed a resolution asking the South Carolina Department of Environmental Services to establish an air quality monitoring station on the city’s east side. The request follows concerns about air pollution from the NorthMark and Valara data center’s 457-megawatt natural gas turbines, though the resolution is not binding on the state agency.

10/21/2026
Spartanburg County weighs new rules for data center development
News ClipFOX Carolina News·Spartanburg County, SC

Spartanburg County weighs new rules for data center development

Spartanburg County officials are considering amendments to local zoning rules for future data center projects, including setbacks, buffers, noise controls and limits on where larger facilities can be built. The county’s temporary moratorium remains in place while officials develop permanent regulations, amid resident concerns about the Valara project’s proximity to homes and schools and its potential environmental impacts.

10/21/2026
Judge tosses lawsuit against data center and Spartanburg County over land development rules
News ClipPost and Courier·Spartanburg County, SC

Judge tosses lawsuit against data center and Spartanburg County over land development rules$

A South Carolina judge dismissed a lawsuit brought by the Southern Environmental Law Center and nearby residents challenging Spartanburg County’s approval of NorthMark Strategies subsidiary Valara’s data center and adjacent 457-megawatt natural gas plant. The plaintiffs lacked standing and failed to exhaust administrative remedies, but the environmental group plans to appeal while construction continues.

10/7/2026
Data center emissions dispute prompts Virginia trip by Spartanburg officials
News ClipFOX Carolina News·Spartanburg County, SC

Data center emissions dispute prompts Virginia trip by Spartanburg officials

The Southern Environmental Law Center is asking South Carolina’s environmental agency to reopen public comments on Valara’s Spartanburg County data center air permit, arguing updated formaldehyde emissions data was not publicly disclosed. Valara also faces at least two active lawsuits, while Spartanburg County officials are traveling to Loudoun County, Virginia, to study its data center industry and meet with industry representatives.

10/6/2026
SC law firm asks regulators to reconsider Spartanburg data center decision
News ClipPost and Courier·Spartanburg County, SC

SC law firm asks regulators to reconsider Spartanburg data center decision$

The Southern Environmental Law Center (SELC) has asked the South Carolina Public Service Commission to reconsider its ruling that certain energy regulations do not apply to data centers that generate their own power. This challenge targets the NorthMark and Valara data center in Spartanburg, which includes a 457-megawatt natural gas power plant. The SELC argues the ruling bypasses oversight for private power plants and sets a concerning precedent.

9/28/2026
After SC data center's projected water use ballooned to 1.4M gallons, it took months to tell public
News ClipPost and Courier·Spartanburg County, SC

After SC data center's projected water use ballooned to 1.4M gallons, it took months to tell public$

Valara, a data center subsidiary of NorthMark in Spartanburg, South Carolina, initially reported a significantly lower water usage estimate of 459,400 gallons per day to Spartanburg Water. However, updated projections revealed the data center would require between 1.4 million and 1.6 million gallons daily, a figure that took seven months to be publicly corrected by NorthMark. Despite the dramatic increase, Spartanburg Water assured that the local infrastructure can handle the updated demand.

9/23/2026
Spartanburg County joins other SC counties in data center moratoriums
News ClipWYFF·Spartanburg County, SC

Spartanburg County joins other SC counties in data center moratoriums

Spartanburg County Council has approved a temporary one-year moratorium on most new data center developments, making it one of several South Carolina counties to enact such a ban. The decision stems from resident and environmental group concerns over rapid growth, electricity demand, and the need for more regulation. Projects with existing permits, like the Valara data center, are not impacted.

9/22/2026
News ClipFOX Carolina News·Spartanburg County, SC

Spartanburg County leaders question pollution monitoring as Valara data center adds more turbines

Spartanburg County leaders are questioning the pollution monitoring protocols for the Valara data center, a nearly $3 billion project under construction. Concerns focus on formaldehyde emissions from natural gas turbines and the accuracy of monitoring methods. Simultaneously, the County Council is considering a one-year moratorium on new data center projects, and a lawsuit seeking to halt the Valara project is currently under judicial review.

9/22/2026
Spartanburg data center gets OK from SC regulators to generate 457 megawatts
News ClipPost and Courier·Spartanburg County, SC

Spartanburg data center gets OK from SC regulators to generate 457 megawatts$

State regulators in South Carolina have approved a permit for NorthMark and Valara to expand their Spartanburg data center to 457 megawatts, despite significant environmental concerns from local residents. The Southern Environmental Law Center (SELC) has criticized the permit and is representing residents in an ongoing lawsuit against Spartanburg County regarding the land development permits for the project. The lawsuit argues the county improperly approved the project as minor developments, bypassing public input.

9/21/2026
Arguments heard in court over Valara data center in Spartanburg Co.
News Clip2:49WSPA 7News·Spartanburg County, SC

Arguments heard in court over Valara data center in Spartanburg Co.

A judge heard arguments in court regarding lawsuits and an injunction to pause construction of the Valara data center in Spartanburg County, South Carolina. Key points of contention included whether the project constitutes a major or minor land development and the potential harms faced by nearby residents. A decision is expected in weeks, but construction at the site continues.

9/17/2026
Environmental group faces off with Spartanburg County during injunction argument
News ClipPost and Courier·Spartanburg County, SC

Environmental group faces off with Spartanburg County during injunction argument$

An environmental group, the Southern Environmental Law Center (SELC), has filed a lawsuit against Spartanburg County and data center developer Valara. The lawsuit challenges the county's classification of a 457-megawatt data center as a 'minor' land use development, which allowed it to bypass public input. A judge is hearing arguments on motions to dismiss and an injunction to halt construction.

9/17/2026
Valara data center construction at center of Spartanburg Co. court hearing
News Clipwspa.com·Spartanburg County, SC

Valara data center construction at center of Spartanburg Co. court hearing

A court hearing was held in Spartanburg County, South Carolina, regarding the Valara data center, addressing lawsuits against its developers and a motion for an injunction to pause construction. The primary arguments revolved around whether the project constitutes a 'minor' or 'major' land development under county ordinances, and the transparency of its scope. The judge deferred a decision on the motions, allowing construction to continue.

9/17/2026
How SC data center is tied to a British financier with an F1 team
News ClipPost and Courier·Spartanburg County, SC

How SC data center is tied to a British financier with an F1 team$

A data center project by NorthMark Strategies and Valara in Spartanburg, South Carolina, is under construction and has already drawn criticism from residents over environmental impacts and high water usage. The article investigates the data center's ties to British financier Peter de Putron and his company, Dorilton Capital Management, which acquired the Williams Formula One racing team.