STACK

Data Center Signal is tracking 5 clips about STACK data center developments across 3 states, including NM, LA, VA.

Loading...
5Clips
3States

States

Topics

government80%
legal80%
opposition80%
zoning60%
electricity60%
environmental60%
water60%
announcement40%
moratorium20%
Timeline: The evolution of Project Jupiter
News ClipSanta Fe New Mexican·Santa Teresa, Doña Ana County, NM

Timeline: The evolution of Project Jupiter$

Project Jupiter, a large AI data center in Santa Teresa, New Mexico, has faced significant legal and environmental challenges, including protests, lawsuits, and a Supreme Court stay on permits, which was recently lifted. Developers Oracle and BorderPlex Digital Assets have announced a new plan to power the facility with natural gas fuel cells to reduce emissions, as various government entities continue to weigh in on its development and associated impacts.

9/18/2026
Project Jupiter site work continues, despite high court’s pause on permits
News ClipSearchlight New Mexico·Santa Teresa, Doña Ana County, NM

Project Jupiter site work continues, despite high court’s pause on permits

Site work continues for Project Jupiter, a massive data center supporting AI for Oracle and OpenAI in Santa Teresa, New Mexico, despite a state Supreme Court order pausing key permits. The project faces criticism over its high water usage, environmental impact, and failure to meet local hiring promises, as reported by Oracle.

8/31/2026
Project Jupiter site work continues, despite high court's pause on permits
News ClipSanta Fe New Mexican·Santa Teresa, Doña Ana County, NM

Project Jupiter site work continues, despite high court's pause on permits

Construction for Project Jupiter, a massive data center supporting Oracle and OpenAI in Santa Teresa, New Mexico, continues despite a state Supreme Court order halting key water and air quality permits. The project faces criticism regarding its significant water usage and the developer's inability to track local hiring, with many workers commuting from out of state and expressing opposition to the data center's environmental impact.

8/31/2026
Northwest Louisiana's Data Center Event Connects Local Businesses At Shreveport Convention Center
News ClipNews Radio 710 KEEL·Shreveport, Caddo County, LA

Northwest Louisiana's Data Center Event Connects Local Businesses At Shreveport Convention Center

Shreveport is hosting a data center supplier outreach event on May 13, 2026, for local businesses to connect with the STACK and Amazon data center projects in Northwest Louisiana. Attorney William Bradford stated the goal is to involve local contractors and vendors as construction ramps up, highlighting a recent court ruling that allowed the West Shreveport project to proceed.

5/7/2026