Project Jupiter site work continues, despite high court's pause on permits

Project Jupiter site work continues, despite high court's pause on permits

News ClipSanta Fe New Mexican·Santa Teresa, Doña Ana County, NM·8/31/2026

Construction for Project Jupiter, a massive data center supporting Oracle and OpenAI in Santa Teresa, New Mexico, continues despite a state Supreme Court order halting key water and air quality permits. The project faces criticism regarding its significant water usage and the developer's inability to track local hiring, with many workers commuting from out of state and expressing opposition to the data center's environmental impact.

environmentalgovernmentlegalelectricitywateropposition
OracleOpenAI
Gov: New Mexico Supreme Court, New Mexico Environment Department, State Engineer’s Office, State Land office, Doña Ana County commissioners, New Mexico Department of Workforce Solutions, Rep. Sarah Silva

Construction for Project Jupiter, a large data center campus near Santa Teresa, New Mexico, continues despite a New Mexico Supreme Court order that paused critical water use and air quality permits. The project, being developed by Oracle and STACK to support artificial intelligence for Oracle and OpenAI, is set to be one of the largest data centers in the nation, spanning over 1,000 football fields.

The data center has drawn criticism for its significant water consumption, having pumped over 103 million gallons of fresh water from an emergency well since April before the Supreme Court halt. Additionally, Oracle's commitment to local hiring is under scrutiny, as the company identified only 189 Doña Ana County residents and 404 New Mexico residents out of more than 2,100 construction workers, with records for 1,600 workers unmatched to a ZIP code. State Representative Sarah Silva of Las Cruces criticized Oracle, stating that the company, despite its expertise in data collection, appears to prioritize rapid construction over local hiring.

Workers on the site, many of whom commute from states like Arizona and Texas, expressed concerns about the project's environmental impact, particularly its water usage. Carson Emery, a construction worker relocated from Houston, voiced his opposition, saying, "They’re taking all of our water." Despite the legal pauses, workers noted that construction supervisors provide minimal updates, and work has continued even at the West Microgrid site, which was intended for natural gas turbines but is now theoretically obsolete after developers withdrew an application in favor of fuel cells.