Data Center Signal is tracking 6 clips about Nebo North LLC data center developments across 1 states, including UT.

Loading...
6Clips
1States

States

Topics

opposition100%
government100%
zoning100%
electricity50%
environmental50%
announcement33%
water33%
moratorium17%
Mona residents question approval process for proposed $10B data center
News Clip1:21KSL News Utah·Mona, Juab County, UT

Mona residents question approval process for proposed $10B data center

Mona residents are actively questioning the approval process for a proposed $10 billion data center in their community, citing a lack of public awareness and proper notification regarding the conditional use permit that allowed the project to proceed. They are seeking answers from the Juab County Commission about public engagement opportunities.

9/11/2026
Mona residents demand answers over data center
News Clip2:36KSL News Utah·Mona, Juab County, UT

Mona residents demand answers over data center

Residents of Mona, Utah, discovered a data center project was approved in Juab County months after the fact, sparking anger over a perceived lack of transparency. A local group, Mona Cares, is organizing residents and demanding the county reverse the conditional use permit.

9/9/2026
Mona, Utah, residents challenge data center approval after permit granted
News ClipDeseret News·Mona, Juab County, UT

Mona, Utah, residents challenge data center approval after permit granted

Residents of Mona, Utah, are protesting the approval of a massive data center project, Nebo North LLC, after learning about it months after its conditional use permit was granted. They accuse Juab County of a lack of transparency, particularly regarding differing notification processes for conditional use permits versus zoning changes. The project, developed by The SetSquare Capital Group, is moving forward despite the growing local opposition, with concerns raised about noise, heat, traffic, and the need for a new gas-powered plant.

9/9/2026
Mona residents criticize county commission over proposed data center
News Clip3:00ABC4 Utah·Mona, Juab County, UT

Mona residents criticize county commission over proposed data center

Mona residents are criticizing the Juab County Commission over a proposed data center near their homes. They expressed concerns about the approval of a conditional use permit without adequate public notification. Residents are worried about the project's size, water and electricity consumption, and noise pollution.

9/8/2026
‘We didn’t get to participate’: Mona residents criticize county commission over proposed data center
News ClipABC4 Utah·Mona, Juab County, UT

‘We didn’t get to participate’: Mona residents criticize county commission over proposed data center

Mona, Utah residents are actively protesting a proposed data center in Juab County after a conditional use permit was approved without what they consider proper public notice. Citizens expressed strong opposition at a Juab County Commission meeting, citing concerns over the project's size, proximity to homes, and the lack of community involvement in the decision-making process. The commission acknowledged shortcomings in public notification but stated legal requirements were met.

9/8/2026
Mona, Utah, residents concerned about approved data center campus
News ClipDeseret News·Mona, Juab County, UT

Mona, Utah, residents concerned about approved data center campus

Residents in Mona, Utah, are expressing concerns about a large data center campus planned by Nebo North LLC, which received a conditional use permit without their prior notice. The article highlights community opposition to similar developments in Texas, including a statewide pause on new data centers ordered by Governor Greg Abbott, and urges Utahns to fight for their local environment and heritage.

8/30/2026