Michigan expanded data center tax breaks. Here’s what they actually cover
News ClipBig Rapids Pioneer·MI

Michigan expanded data center tax breaks. Here’s what they actually cover$

Michigan expanded its sales and use tax exemptions for data centers through new 2024 legislation, extending existing breaks until 2050 and introducing an "enterprise data center" category for larger investments. These expanded incentives require significant capital investment, job creation, and specific environmental and clean energy commitments to qualify. The legislation aims to make Michigan more competitive for major data center development.

8/24/2026
EXPLAINER: Is it a data center? How GenH’s Morley Dam concept would work
News ClipBig Rapids Pioneer·Morley, Mecosta County, MI

EXPLAINER: Is it a data center? How GenH’s Morley Dam concept would work$

GenH is exploring a concept to build small computing facilities, described as digital service centers, powered by hydroelectricity at existing dams, including the Morley Dam in Michigan. The company held a public meeting in Morley to gauge community interest, where residents raised concerns about environmental impacts, noise, and water use. GenH emphasized its model's smaller scale and independent power supply, which differentiates it from larger data centers.

8/23/2026
Morley residents push back on hydropower concept at village dam
News ClipHuron Daily Tribune·Morley, Mecosta County, MI

Morley residents push back on hydropower concept at village dam$

Residents of Morley, Michigan, turned out in force to question GenH about its proposal to use the Frank Deyo Dam for a small hydroelectric computing facility. Strong community opposition was voiced regarding environmental impacts, noise, and the company's approach, though potential village revenue was also noted. The village board is exploring legal constraints related to the dam's deed and considering regulatory options, including a moratorium, before any formal proposal is considered.