SpaceXAI Faces More Than $136 Million in Contractor Lien Claims Over Memphis AI Data Centers
SpaceXAI is facing over $136 million in mechanic's lien claims in Shelby County, Tennessee, from contractors like Darana Hybrid, USW-Menard Inc., and TorcSill Foundations. These claims allege non-payment for work performed on its AI data centers in the Memphis area. The dispute highlights financial pressures on contractors and suggests potential additional claims totaling $400 million may be filed in Mississippi.