ATC asks feds to reopen bidding for Wisconsin transmission project
American Transmission Company (ATC) has asked the Federal Energy Regulatory Commission (FERC) to intervene in a dispute over a major transmission project in eastern Wisconsin. The project, initially awarded to Viridon, is crucial for connecting a large data center campus in Port Washington to the grid by late 2027. ATC's appeal challenges the competitive bidding process, seeking to either redo the bidding or be awarded the full project to ensure timely grid connection for the data center.