News ClipKFOX·Santa Teresa, Dona Ana County, NM
Proposed 17-mile natural gas pipeline for Project Jupiter data center under review
A proposed 17.7-mile natural gas pipeline, the Green Chile Pipeline Project, for the Project Jupiter data center in Doña Ana County, New Mexico, is under federal review by the Federal Energy Regulatory Commission. The pipeline is intended to supply on-site power generation for the data center, which is also seeking air quality permits from the New Mexico Environment Department. Key decisions and public comment deadlines are set for April 13.
3/23/2026