PPL outlines plans for new power plants to serve Salem Township data center
PPL Corporation outlined plans for two natural gas-fired power plants and additional fuel-cell and battery-storage facilities to supply QTS's proposed data center in Salem Township. The generation project could add about 2,000 megawatts of capacity and cost an estimated $5 billion to $7 billion, with the gas plants expected to begin operating in 2032 and 2033.