Invitium Energy

Data Center Signal is tracking 4 clips about Invitium Energy data center developments across 1 states, including PA.

Loading...
4Clips
1States

States

Topics

electricity100%
government50%
opposition50%
announcement25%
environmental25%
zoning25%
PPL outlines plans for new power plants to serve Salem Township data center
News ClipNorthcentralPA.com·Salem, Luzerne County, PA

PPL outlines plans for new power plants to serve Salem Township data center

PPL Corporation outlined plans for two natural gas-fired power plants and additional fuel-cell and battery-storage facilities to supply QTS's proposed data center in Salem Township. The generation project could add about 2,000 megawatts of capacity and cost an estimated $5 billion to $7 billion, with the gas plants expected to begin operating in 2032 and 2033.

11/13/2026
PPL buys 230 acres in Archbald near Aylesworth Park for $4 million
News ClipScranton Times-Tribune·Archbald, Lackawanna County, PA

PPL buys 230 acres in Archbald near Aylesworth Park for $4 million

PPL Electric Utilities bought more than 230 acres in Archbald for $4 million to support future transmission infrastructure, not to build a data center or power plant. The property is near proposed data center campuses and a broader PPL-Blackstone venture, drawing criticism from Lackawanna County Commissioner Bill Gaughan over potential industrial development in the region.

10/27/2026
Data centers drive PPL’s 31.8 GW pipeline as PUC sees industrial power up 51% a year
News ClipLehigh Daily·PA

Data centers drive PPL’s 31.8 GW pipeline as PUC sees industrial power up 51% a year

Industrial electricity use in PPL Electric Utilities' Pennsylvania service territory is projected to surge by 51% annually through 2030, driven primarily by data center development. PPL is planning a 31.8 GW data center pipeline, with a joint venture, Invitium Energy, securing land and interconnection requests. The Pennsylvania Public Utility Commission has issued guidance on tariffs for large-load customers to ensure they fund necessary infrastructure, addressing concerns about costs shifting to existing consumers.

9/8/2026
AI boom drives plans for Pennsylvania data-center-only power plants, with 5 gigawatts reserved
News Clipthecooldown.com·PA

AI boom drives plans for Pennsylvania data-center-only power plants, with 5 gigawatts reserved

An AI boom is driving plans for data-center-specific power plants in Pennsylvania, with Invitium Energy, a joint venture of PPL Corp. and Blackstone Infrastructure, reserving 5 gigawatts of combined-cycle gas turbines. This development raises environmental concerns due to reliance on fossil fuels, while politicians are responding to public opposition. Kentucky's Governor Beshear has signed an executive order requiring data center developers to prove no harm to ratepayers or air/water quality.

8/13/2026