TeraWulf acquires site in Greenup for 1+ GW data center campus
News ClipLane Report·Greenup County, KY

TeraWulf acquires site in Greenup for 1+ GW data center campus

TeraWulf has acquired a 285-acre site in Greenup County, Kentucky, for its new Muskie Data Campus, which is planned to be a 1+ gigawatt data center operation. The initial 500 MW capacity is expected by late 2028, supported by a new 345 kV substation being constructed by Kentucky Power. The site is already zoned for its intended use and is seen as a significant economic development for the region.