Fort Worth could ban cryptocurrency mining. Data centers might be here to stay
News ClipFort Worth Report·Fort Worth, Tarrant County, TX

Fort Worth could ban cryptocurrency mining. Data centers might be here to stay

Fort Worth city officials are proposing new regulations for data centers, including specific zoning standards, noise limits, water efficiency requirements, and a prohibition on cryptocurrency mining as a primary use. The City Council will vote on these proposals in August, while the zoning commission will vote in July, amid ongoing resident concerns and calls for a moratorium.

6/4/2026
City Council to discuss future of data centers in Fort Worth as residents push back
News ClipFort Worth Report·Fort Worth, Tarrant County, TX

City Council to discuss future of data centers in Fort Worth as residents push back

The Fort Worth City Council is set to discuss data center regulations, including zoning and resource usage, following significant residential opposition. Residents are concerned about land, energy, water use, and noise, and have launched a campaign for a moratorium on new data center construction in the city. The discussion will inform potential new guidelines for data center development.

5/29/2026
Planned $1.1B data center campus near Benbrook could break ground this summer
News ClipFort Worth Star-Telegram·Fort Worth, Tarrant County, TX

Planned $1.1B data center campus near Benbrook could break ground this summer

Edged Data Centers, a subsidiary of Endeavor, is planning a $1.1 billion data center near Veale Ranch in Fort Worth, Texas. Initial construction paperwork has been filed with the Texas Department of Licensing and Regulation for a project estimated at $300 million for its first phase. The developer recently withdrew an application for a city tax agreement amidst resident scrutiny, though the project has secured ERCOT approval.

5/19/2026
Fort Worth prepares for data center policy discussions amid public opposition
News ClipKERA News·Fort Worth, Tarrant County, TX

Fort Worth prepares for data center policy discussions amid public opposition

Fort Worth leaders are initiating discussions regarding data center development policies in response to growing public concern over environmental impact and quality of life. This comes as residents organize to urge a halt on new projects, and city officials have tabled or delayed decisions on proposed tax breaks and rezonings for companies like Edged Data Centers and Black Mountain. The city is preparing a report to guide future decisions, focusing on zoning, environmental impact, and utility usage.

5/18/2026
‘Enough concern today’: $1B data center stalls; city, residents raise questions about tax break
News ClipFort Worth Report·Fort Worth, Tarrant County, TX

‘Enough concern today’: $1B data center stalls; city, residents raise questions about tax break

The Fort Worth City Council tabled a vote on a 50% tax abatement for Edged Data Centers' proposed $1 billion waterless facility in Veale Ranch. This delay stems from council members' and residents' concerns regarding the project's economic benefits, environmental impact, and demands for stricter regulations on data center development in the city.

3/31/2026
Fort Worth City Council delays vote on tax abatement for proposed $1.1B data center amid resident concerns
News ClipWFAA·Fort Worth, Tarrant County, TX

Fort Worth City Council delays vote on tax abatement for proposed $1.1B data center amid resident concerns

The Fort Worth City Council has delayed a vote on a proposed 10-year tax abatement for Edged Data Centers' $1.1 billion data center project in southwest Tarrant County. The delay comes after residents raised concerns about transparency, noise levels, and water usage, marking the second time this month such concerns have been voiced over a data center in the city. Councilman Michael Crain postponed the vote to allow more discussion and has requested a city report on data center development rules.

3/31/2026
Fort Worth delays vote on tax break for $1.1B data center as concerns grow
News ClipFort Worth Star-Telegram·Fort Worth, Tarrant County, TX

Fort Worth delays vote on tax break for $1.1B data center as concerns grow

The Fort Worth City Council delayed a vote on a tax agreement for Edged Data Centers' proposed $1.1 billion AI data center in west Fort Worth. The delay was prompted by significant resident concerns regarding the project's impact and the city's handling of data center developments. The council agreed to postpone the vote until May 12 to address these issues.

3/31/2026
Fort Worth to vote on tax break agreement for developers of $1.1B data center
News ClipFort Worth Star-Telegram·Fort Worth, Tarrant County, TX

Fort Worth to vote on tax break agreement for developers of $1.1B data center

The Fort Worth City Council is set to vote on a tax break for Edged Data Centers' proposed $1.1 billion data center. Residents in Fort Worth and Benbrook have voiced concerns about potential noise, environmental risks, and traffic, forming a coalition to advocate for transparency from developers. Council members are balancing economic growth with community impact.

3/30/2026
Fort Worth data center promises sustainability. Residents ask for transparency
News ClipFort Worth Report·Fort Worth, Tarrant County, TX

Fort Worth data center promises sustainability. Residents ask for transparency

Fort Worth residents are demanding transparency and environmental studies from Edged Data Centers and city officials regarding a proposed data center and a significant tax abatement. The City Council is set to vote on the tax break, despite ongoing community concerns about resource usage and impacts on neighborhoods. A separate data center project by Black Mountain in the same region is also facing community opposition.

3/26/2026
Fort Worth, Benbrook residents meet with developers proposing $1.1B data center
News ClipFort Worth Star-Telegram·Fort Worth, Tarrant County, TX

Fort Worth, Benbrook residents meet with developers proposing $1.1B data center

Fort Worth and Benbrook residents met with developers from Edged Data Centers to discuss a proposed $1.1 billion data center on the city's west side. Residents raised concerns about environmental impact, noise levels, water usage, and the city's zoning notification process. The Fort Worth City Council is scheduled to vote on an economic development agreement for the project soon.

3/25/2026
Fort Worth council member requests data center report ahead of residents meeting
News ClipFort Worth Star-Telegram·Fort Worth, Tarrant County, TX

Fort Worth council member requests data center report ahead of residents meeting

Fort Worth City Council member Michael Crain has requested a report on how the city evaluates and approves data center projects, including incentives. This comes ahead of a meeting where residents of Fort Worth and Benbrook will discuss concerns about a proposed $1.1 billion data center by Edged Data Centers, citing traffic, noise, and water usage impacts. The Fort Worth City Council is set to consider an economic development agreement for the project.

3/24/2026
Residents join together to question data center proposal in west Fort Worth
News ClipFort Worth Star-Telegram·Fort Worth, Tarrant County, TX

Residents join together to question data center proposal in west Fort Worth

Residents in Benbrook and Fort Worth, Texas are organizing to voice their concerns about a proposed $1.1 billion data center development in west Fort Worth. They are raising questions about the potential health and environmental risks, as well as the impact on the local power grid. The Fort Worth City Council is considering a tax break for the data center project, which will be discussed at an upcoming meeting.

3/17/2026