Ohio Supreme Court Says Lordstown Can Reject Data Center Site-Plan Review
The Supreme Court of Ohio ruled that Lordstown did not have to process Bristolville 25 Developer LLC's site-plan review for four proposed data centers because the developer had not completed the required preliminary steps before the village's data-center moratorium took effect. Lordstown's moratorium was extended for 180 days and is scheduled to expire in January 2027, while regional officials say they may seek another site for the project.