Judge denies company’s request to end Springfield’s data center moratorium
A judge rejected NSI’s request to proceed with a proposed data center in Springfield despite the city’s moratorium, allowing the ruling to stand. Springfield City Council is expected to consider extending the moratorium through February, while a separate Benton County case remains pending.
A judge denied tech company NSI’s request to end Springfield’s data center moratorium and proceed with plans for a facility at 2900 South National Avenue. NSI argued that the property’s zoning permits "data processing services" and that city planners approved the project before the moratorium took effect, but the ruling did not favor the company.
The Springfield City Council is expected to vote Nov. 16 on extending the moratorium until February. In a separate case, another judge temporarily blocked Benton County from enforcing its moratorium against NSI, pending a final judgment; no court date has been set.