Eagan Sues IronGate Data Center Over Noisy, Unpermitted Chillers
The City of Eagan sued Eagan Capital LLC over four temporary chillers at the IronGate Data Center, alleging they were installed without required permits and exceeded noise limits. The Eagan City Council also denied a six-month permit for the chillers and has adopted a one-year moratorium on certain new data centers, which Eagan Capital is separately challenging in court.
The City of Eagan filed a lawsuit against Eagan Capital LLC over four temporary chillers operating at the IronGate Data Center on Pilot Knob Road without the permits officials say were required. Residents complained about noise, and an applicant-commissioned study found that the chillers exceeded city and state noise thresholds. The city said it may seek an injunction to stop their operation.
The Eagan City Council unanimously rejected a six-month interim-use permit for the chillers, determining that the proposed use was not lawful under the property's current zoning. Separately, Eagan Capital sued the city over a one-year moratorium adopted in February 2026 that applies to new data centers near homes or using more than 20 megawatts of electricity. The moratorium is scheduled to remain in effect until Feb. 17, 2027, while the city studies potential impacts and the company's lawsuit seeks damages and challenges the city's authority to impose the suspension.