Green Charter Township extends data center moratorium, hears ITC concerns

Green Charter Township extends data center moratorium, hears ITC concerns

News ClipBig Rapids Pioneer·Green Charter, Mecosta County, MI·11/12/2026

Green Charter Township approved a six-month extension of its data center moratorium to give the planning commission more time to develop a permanent ordinance. Residents also opposed proposed ITC Copperton Project transmission routes, citing impacts to farms, homesites and the environment.

moratoriumoppositionenvironmentalgovernment
Gov: Green Charter Township Board of Trustees, Green Charter Township Planning Commission

The Green Charter Township Board of Trustees extended the township’s data center moratorium for six months during its Nov. 10 meeting. Township Supervisor Jason Kruse said the additional time was needed for the planning commission to develop a permanent data center ordinance.

Residents separately urged the board to oppose proposed ITC Copperton Project transmission routes through the township, saying the lines could cross farms and homesites and create environmental hazards. Kruse said he would research the project and a possible opposition resolution for consideration at a future meeting. The board also authorized distribution of a draft master plan to surrounding communities for review before a future public hearing and adoption vote.