Van der Vaart dissents on Duke rates, data centers before resignation
North Carolina Utilities Commission member Donald van der Vaart announced his resignation after dissenting from a ruling on Duke Energy rates and a new data center tariff. He warned that the commission’s approach could leave ordinary ratepayers responsible for billions of dollars in generation costs if data centers leave before power plants are paid off.
Donald van der Vaart will resign from the North Carolina Utilities Commission effective Jan. 1 after issuing a partial dissent over Duke Energy’s rate increase and a new tariff for data center customers. Van der Vaart argued that the order shifts too much risk from Duke Energy to other customers and approved a return on equity that does not adequately reflect that risk.
His dissent said Duke has signed contracts for about 6.7 gigawatts of new load across the Carolinas, nearly all from data centers, with another 7.9 gigawatts of potential large load in advanced development. Van der Vaart estimated that serving the signed load could require $18 billion to $19 billion in new generation investments, while data center contracts may last only 15 years compared with the roughly 35-year life of the power plants.
Van der Vaart supported some provisions of the commission’s tariff, including requiring data centers to pay for dedicated facilities and rejecting grandfathering. However, he said the order still leaves general ratepayers as the ultimate backstop for stranded generation costs. State Treasurer Brad Briner, who nominated van der Vaart, said he would announce a replacement in the coming weeks.