Utah startup submits plan for nuclear-powered data centers. As it seeks its first permit, here’s what we know.
Valar Atomics has submitted a conditional-use permit application for the Raceway Energy Campus near Wellington in Carbon County, including data center buildings, nuclear reactors, fuel facilities and supporting power infrastructure. Carbon County leaders are preparing to review the proposal, while opponents plan to ask officials to slow the project and impose conditions related to safety, water use and environmental impacts.
Valar Atomics is seeking approval to develop the Raceway Energy Campus on about 640 acres of Utah state trust land near Wellington in Carbon County. The proposed campus would include data center buildings, dozens of small nuclear reactors, nuclear fuel manufacturing and spent-fuel storage, with a natural gas plant, transmission lines, batteries and substations providing power before the reactors are operational and during peak demand.
The company argues the project qualifies as a conditional use under the county's existing mining and grazing zoning. The Carbon County Planning Commission is scheduled to consider the permit at a special meeting, giving county officials their first formal opportunity to review the proposal and set operating conditions. Opponents intend to attend in large numbers and are urging the county to proceed more slowly, citing potential health, safety, water and environmental concerns.