Data center developers remove special use application for data center, approved for light industrial
News ClipAccessWDUN·Gainesville, Hall County, GA·12/11/2025
Data center developers in Gainesville, Georgia have withdrawn their special use permit application for a data center project called 'Project Turbo' and instead received approval for a light industrial zoning designation. This decision was met with surprise from the hundreds of local residents who attended the county commission meeting.
zoningannouncement
Gov: Hall County Board of Commissioners
The Project Turbo data center vote took the hundreds of residents in attendance by surprise: the developers rescinded their special use permit for a data center.