State consumer advocate files complaint against data centers
Pennsylvania's consumer advocate filed a complaint with the Public Utility Commission arguing that PPL Electric Utilities' rules could shift data center-related grid costs and reliability risks onto existing customers. Gov. Josh Shapiro's office has intervened, while the case remains in its early stages and could establish statewide principles for data center electricity costs.
Pennsylvania Consumer Advocate Darryl Lawrence filed a complaint with the Pennsylvania Public Utility Commission in October, arguing that PPL Electric Utilities should make data centers pay the full costs of grid upgrades and bear greater responsibility for reliability risks. The complaint also seeks stronger protections for existing customers, including requirements to reduce data center service during grid emergencies and increased contributions to low-income assistance programs.
Gov. Josh Shapiro's office intervened in the proceeding after the governor signed an executive order encouraging data center developers to provide their own electricity supply and pay for necessary grid upgrades. PPL said it supports protecting customers, maintaining reliability and ensuring large-load customers pay project-related costs, but the consumer advocate argues the utility's existing rules and proposed changes do not go far enough.
The proceeding cites a planned $178 million transmission project in Luzerne County that would serve a potential data center campus. PPL currently plans to recover about 12% of those costs from the data center, leaving the consumer advocate concerned that existing customers could be responsible for the remaining amount. A final commission decision is not expected until next July.