Oracle's Project Jupiter Faces Delays, Stock Declines After Force Majeure Notice

News Clippinonpost.com·Santa Teresa, Doña Ana County, NM·9/29/2026

Oracle's Project Jupiter, a massive AI data center in Santa Teresa, New Mexico, is facing significant delays due to power supply issues, prompting Oracle to invoke a force majeure provision. This contractual action has led to a notable decline in Oracle's stock price and increased scrutiny from investors regarding the project's financing and timeline. The project continues to grapple with permitting delays for its natural gas pipeline and an air-quality permit for its fuel cell operations.

electricityenvironmentaloppositiongovernmentlegal
Oracle

Oracle's Project Jupiter, an ambitious artificial intelligence data center complex under construction in Santa Teresa, New Mexico, is experiencing significant setbacks. The technology giant recently invoked a force majeure provision due to potential delays in securing the immense amount of power required for the facility, estimated at 2.45 gigawatts.

This contractual action has drawn considerable attention from Wall Street, contributing to a slide in Oracle's stock. Oracle shares fell approximately 8.3% after the news became public, as investors grew concerned about financing risks and the project's ability to meet its targeted operational date of 2028. STACK Infrastructure, a subsidiary of Blue Owl Capital, is developing the project, while Bloom Energy is slated to provide fuel cells, and both companies were affected by the market reaction.

Project Jupiter's power system has been a consistent source of complications, including permitting delays for a natural gas pipeline and an outstanding air-quality permit for the fuel-cell operation. While Oracle maintains that Project Jupiter remains on schedule and reiterates its commitment to New Mexico, the force majeure invocation and market response highlight the challenges of bringing large-scale AI infrastructure online. The project has also faced ongoing controversies related to water, electricity, permitting, government incentives, and opposition from local residents.