Memphis Mayor Young Discusses Proposed Data Center Moratorium
Memphis Mayor Young said the city is working under a 90-day executive order concerning data centers. Officials are considering creating a separate zoning category for data centers, with rules based on power consumption and project intensity, while seeking input from environmental stakeholders and residents.
Memphis Mayor Young said the city is evaluating data center development under a 90-day executive order. Chief Operating Officer Chris Winton briefed the City Council on preliminary zoning ideas, noting that data centers are currently treated as office uses and are permitted across many commercial zoning districts.
The administration is considering a separate data center zoning category that would classify projects by power demand, including megawatt usage, and determine where they could be located and when City Council approval would be required. Officials have consulted environmental stakeholders and community members and plan to hold public meetings before advancing the proposals.