Botetourt County sued over Google Data Center, next hearing scheduled for Nov. 16

News Clip2:08WSLS 10·Botetourt County, VA·11/10/2026

A lawsuit challenging Botetourt County’s approval of a proposed 300-acre Google data center campus will proceed after a circuit court judge denied a motion to dismiss. The plaintiff is seeking an injunction that would halt work and invalidate performance agreements, while the county says construction has begun and an injunction would unfairly harm the county and third parties.

oppositiongovernmentlegal
Google
Gov: Botetourt County Board of Supervisors, Botetourt County Circuit Court

A Botetourt County Circuit Court judge denied a motion to dismiss a lawsuit brought by county resident Robert Dallas against Botetourt County and Helios, a Google-related shell company. The suit alleges the county violated Virginia’s Freedom of Information Act by approving a performance agreement for the proposed 300-acre Google data center campus without adequately informing the public about the vote.

Dallas and his attorneys are seeking an injunction to stop past, current and future work and to nullify performance agreements signed in 2025. County attorneys argued that officials provided sufficient notice, that the agreement was discussed after the vote, and that construction has already started while the county has spent millions of dollars received from Helios. A subsequent hearing was scheduled for Nov. 16 in Fincastle, with activists continuing to support the challenge.