Pittsburg Approves AVAIO Data Center Amid Opposition and Moratorium on Future Projects
Pittsburg approved AVAIO Digital’s first-phase data center on the former Delta View Golf Course, including a substation and 37 backup diesel generators. The project has drawn a petition with more than 28,000 signatures, environmental concerns, and a lawsuit that was settled, while the City Council enacted a 45-day moratorium blocking future phases and new data centers.
Pittsburg approved the design of AVAIO Digital’s $800 million Perseus data center, a planned 92-megawatt facility on the former Delta View Golf Course. The first phase includes a three-story data center, an electrical substation and 37 backup diesel generators. The project still requires a city power contract, generator permits and approvals related to its water system.
The development has generated substantial opposition, including a petition with more than 28,000 signatures and repeated demonstrations by residents led by Amhari Perkins. The Center for Biological Diversity sued over the environmental review, but the case was settled after the city, AVAIO and Pittsburg Data Hub agreed to measures including recycled water for cooling and landscaping, renewable power commitments, solar installations and local climate funding.
Pittsburg City Council approved a 45-day emergency moratorium on new data centers, including AVAIO’s proposed future phases but exempting the already-approved first phase. The project faces continuing concerns about water availability, diesel-generator emissions, electricity interconnection and potential conflicts involving Mayor Dionne Adams, who works for PG&E and was barred from participating in the related agreement by the state ethics commission.