Faribault to revise data center environmental review after Minnesota court ruling

Faribault to revise data center environmental review after Minnesota court ruling

News ClipKEYC News Now·Faribault, Rice County, MN·6/10/2026

The City of Faribault is required to revise its environmental review for an upcoming Archer Datacenters project. This decision comes after the Minnesota Court of Appeals ruled the city's initial review was insufficient. The court's ruling occurred on Monday, June 8.

environmentallegalgovernment
Gov: City of Faribault, Minnesota Court of Appeals
The City of Faribault says it is committed to revising its environmental review of an upcoming Archer Datacenters project after the Minnesota Court of Appeals ruled it was insufficient on Monday, June 8.