Prologis sues Trenton over voter-approved data center restrictions as Project Mila construction continues
Prologis has sued the city of Trenton in federal court, arguing that a voter-approved charter amendment limiting data centers to 25 megawatts cannot invalidate Project Mila's earlier approvals. The planned 250-megawatt facility continues construction while residents seek to have its zoning certificate revoked and may intervene in the lawsuit.
Prologis is suing Trenton after roughly 80% of voters approved Issue 17, a charter amendment prohibiting data centers with power demand above 25 megawatts. Project Mila is designed for 250 megawatts, but Prologis says it received a zoning certificate in December 2025 and invested tens of millions of dollars before the restriction was approved, giving it a vested right to continue.
Residents and their attorneys argue the amendment supersedes conflicting zoning provisions and have asked the city to revoke Project Mila's certificate. The city says it is awaiting certification of the election results and views the dispute as a matter for the courts; construction remains underway as the federal case proceeds.