Judge rules data center project must undergo full environmental review
News Clipkyma.com·Yuma County, AZ·9/1/2026
A judge has ruled that a data center project must undergo a full environmental review due to sufficient evidence of potential environmental impacts. This decision rejected the county's attempt to classify the project's permits as ministerial actions, requiring a more thorough assessment of its potential effects.
environmentallegalgovernment
Gov: The Court, Yuma County
The court found sufficient evidence of potential environmental impacts, rejecting the county's attempt to treat permits as ministerial actions.