Nevada Public Utilities Commission Approves Data Center Power Plant Permits Despite Public Opposition

News ClipReno Gazette Journal·NV·9/22/2026

The Public Utilities Commission of Nevada approved permits for two massive gas-fueled electricity-generating facilities for data centers, despite significant public opposition. The commission stated it could not consider public comment and ruled that the projects are not required to meet Nevada's Renewable Portfolio Standard or limit greenhouse gas emissions. This decision has sparked concerns regarding the state's environmental goals.

oppositionenvironmentalelectricitygovernment
Gov: Public Utilities Commission of Nevada

The Public Utilities Commission of Nevada (PUCN) recently approved permits for two substantial 'behind the meter' (BTM) gas-fueled electricity-generating facilities intended to power data centers. The decision came during a special meeting where numerous individuals expressed strong opposition, citing concerns that the projects would not serve the public interest, would burn greenhouse gas-emitting methane, and would undermine Nevada's renewable energy goals.

Attendees at the meeting provided extensive public comment, arguing that the facilities failed to meet criteria outlined in NRS 704.890(1). However, a commission attorney informed the public that their comments could not be considered in the decision-making process. The commissioners subsequently ruled that the projects were not obligated to comply with Nevada's Renewable Portfolio Standard nor limit greenhouse gas emissions, and determined that all other criteria were met.

Despite widespread public objection and a recent poll indicating significant national opposition to data center construction in local areas, the PUCN granted permits for both projects. Critics called the outcome "absurd" and warned that similar requests for gas-fueled power plants for data centers are likely to follow, potentially jeopardizing Nevada's emissions reduction targets.