Cumberland County Planning Commission Recommends Approval for Dominion Energy Power Plant
The Cumberland County Planning Commission has recommended approval for Dominion Energy's proposed Cumberland Energy Center, a dual-fuel power station, despite mixed public opinion. The project, which some residents believe is intended to support future data centers in the region, now moves to the Cumberland County Board of Supervisors for a final decision. The proposed plant would generate nearly 3,000 megawatts of electricity and significantly increase the county's tax revenue.
The Cumberland County Planning Commission has voted 5-1 to recommend approval of Dominion Energy's request for a conditional use permit (CUP) for its proposed Cumberland Energy Center. The project, a dual-fuel combined-cycle power station capable of generating nearly 3,000 megawatts of electricity, is slated for 150 acres off Duncan Store Road in an A-2 Agricultural zoning district.
Public opinion at the hearing was divided, with 15 speakers opposing the project and 13 supporting it. Opponents, including resident Tim Martin and Rev. Muriel Miller Branch, raised concerns about environmental impact, property values, and the potential for the plant to primarily support data centers in Northern Virginia. Branch emphasized prioritizing "people over profit" and questioned the commission's integrity regarding the comprehensive plan.
Supporters highlighted the project's economic benefits, including approximately 450 construction jobs, 100 operational jobs, and projected tax revenues exceeding $500 million over the life of the project. Darren Hurley, Coordinator of Emergency Services for Cumberland County, expressed full support, noting the plant could help address critical funding needs for the county's fire and rescue departments. District 2 Commissioner Stephen Donahue was the sole dissenting vote, citing missing stipulations regarding compliance with laws, decommissioning guarantees, and protections for affected neighbors.
The commission's recommendation now sends the permit application to the Cumberland County Board of Supervisors for their consideration. Dominion Energy's timeline suggests planning and development will continue through 2028, with construction beginning in 2029 and completion by 2034.