Rayburn Electric Cooperative Secures Loan for New Plant, Discusses Data Center Vetting and Texas Grid Impact

Rayburn Electric Cooperative Secures Loan for New Plant, Discusses Data Center Vetting and Texas Grid Impact

News ClipThe Texas Energy and Power Newsletter·Sherman, Grayson County, TX·8/26/2026

Rayburn Electric Cooperative secured a $411 million Texas Energy Fund loan to construct a 570 MW gas plant in Sherman. The cooperative is also vetting new data center loads with its own questionnaire, anticipating a doubling or tripling of peak load due to the influx of data centers in Texas. Discussions around transmission cost allocation and Governor Abbott's data center audit are underway, aiming to manage their impact on the grid and ratepayers.

electricitygovernmentzoning
Gov: ERCOT, PUCT, Governor Abbott, Texas Legislature

Rayburn Electric Cooperative has broken ground on a 570 MW gas plant in Sherman, Texas, after securing a $411 million loan from the Texas Energy Fund. This project marks the fund’s first generation loan to a cooperative and is part of Rayburn's strategy to gain more control over its power supply following lessons from Winter Storm Uri. Christian Nagel, Senior Director of Power Supply and Production at Rayburn, highlighted the cooperative's vertically integrated utility model, which combines generation, transmission, and retail services under one roof, allowing for agility in decision-making.

The article emphasizes Rayburn's proactive approach to vetting new data center loads, noting the significant impact these will have on the cooperative’s predominantly residential membership, potentially doubling or tripling its peak load. Rayburn uses a proprietary questionnaire to assess data centers' readiness and financial commitment, requiring upfront payment for interconnection studies and financial security for long lead-time equipment. This process aims to protect existing members from financial risks associated with large, speculative loads.

Nagel also discussed broader regulatory issues affecting data centers in Texas, including Governor Abbott's audit, which has delayed ERCOT’s Batch Zero study, and ongoing efforts by the Public Utility Commission of Texas (PUCT) and the state legislature to re-evaluate transmission cost allocation. Rayburn anticipates that its current agreements with data centers, structured within its tariff, should help lower or stabilize member rates, but the overall impact on Texas ratepayers will hinge on these evolving regulatory frameworks.