
Oracle warns it might not pay data center lease
News ClipMorning Brew·NM·9/25/2026
Oracle has warned the developer of its New Mexico AI data center, Project Jupiter, that it may delay contract payments if the facility isn't operational by 2028. The project faces delays because permits for a critical natural gas pipeline are stalled due to local opposition. Oracle has invoked a force majeure clause in its contract but remains committed to the project.
legaloppositionelectricity
OracleOpenAI
Oracle, a primary tenant, has informed the developer of the