Developer O'Neill claims data center "deemed approved" due to Plymouth Township not meeting hearing requirements

Developer O'Neill claims data center "deemed approved" due to Plymouth Township not meeting hearing requirements

News ClipMoreThanTheCurve·Conshohocken, Montgomery County, PA·11/24/2026

Developer Brian O’Neill claims his proposed data center in Conshohocken has been deemed approved because Plymouth Township allegedly failed to hold a required hearing and meet other statutory deadlines. O’Neill is seeking a special exception for the project at the former steel plant site at 900 Conshohocken Road.

zoning
Gov: Plymouth Township

During a Nov. 19 zoning hearing, developer Brian O’Neill submitted a letter arguing that his proposed data center at 900 Conshohocken Road in Plymouth Township should be considered approved as of June 28, 2026. The site is a former steel plant located in a heavy industrial zoning district.

O’Neill contends that Plymouth Township failed to hold a hearing required under the Pennsylvania Municipalities Planning Code and missed other application-related deadlines. The developer is seeking a special exception to permit the data center, but the article does not report a final township decision on the claim.