Update on Port Washington’s Lighthouse Data Center Campus

Update on Port Washington’s Lighthouse Data Center Campus

News ClipThe Heartland Post·Port Washington, Ozaukee County, WI·11/17/2026

The Lighthouse data center campus in Port Washington, Wisconsin, faces a significant delay because its required transmission-line application was rejected as incomplete and must be refiled. Vantage Data Centers still targets a 2028 opening, but full power capacity could be delayed until 2029 depending on the review process.

electricitygovernmentzoningannouncement
OracleOpenAI
Gov: Public Service Commission of Wisconsin, City of Port Washington

The $15 billion Lighthouse data center campus in Port Washington is under construction, but its timeline is threatened by delays in securing the transmission infrastructure needed to provide full power. The Public Service Commission of Wisconsin rejected American Transmission Company’s initial application as incomplete after extensive changes were made to the proposal, closing the case without ruling on its merits. ATC subsequently submitted a revised plan estimated to cost $2.5 billion to $2.7 billion, restarting the review process.

Vantage Data Centers is developing the four-building, 2.5-million-square-foot campus for Oracle and OpenAI and continues to target an opening in 2028. Analysts estimate partial power could be available in late 2027, while full capacity may not arrive until October 2028 or potentially 2029. Port Washington approved the project and related data center zoning in 2025, and local officials say the development will create thousands of jobs without imposing direct costs on residents. The commission has also adopted a rate structure requiring data centers to cover the full cost of dedicated generation and related fuel, while We Energies says customers will pay for the infrastructure they require.