County data center project delayed until January

County data center project delayed until January

News ClipThe Rapid City Post·Rapid City, Pennington County, SD·11/24/2026

The Pennington County Planning Commission unanimously delayed review of Nodiac Development LLC's conditional use permit for a proposed 20-megawatt data center near Rapid City until Jan. 25, 2027. The project must first complete parcel platting through the City of Rapid City and provide additional information on electrical capacity, noise, stormwater and site requirements.

zoninggovernmentelectricitywater
Gov: Pennington County Planning Commission, Pennington County, Pennington County Planning & Zoning Department, City of Rapid City, Rapid City City Council

The Pennington County Planning Commission voted Nov. 23 to continue review of Nodiac Development LLC's conditional use permit application for a proposed 20-megawatt data center near 7751 Old Folsom Road, south of the Black Hills Industrial Center. The hearing is now scheduled for Jan. 25, 2027, after the developer completes a 10-acre parcel plat through Rapid City's three-mile platting jurisdiction.

County Planning & Zoning Director Brittney Hand said the current 60-acre parcel does not meet the ordinance requirements for the proposed modular facility. The project would include about 17,192 square feet of building space, a closed-loop cooling system using approximately 30,000 gallons of water, and additional electrical infrastructure. Black Hills Electric Cooperative has issued a conditional Will-Serve Letter, but further studies are needed to confirm capacity, while the county is also requesting detailed analyses of noise, vibration and other potential effects on neighboring properties.