FiveC Group Files Permit for $575 Million Memphis Data Center

News Clip0:53ABC24 Memphis·Memphis, Shelby County, TN·10/7/2026

FiveC Group filed a permit for a $575 million data center development at the former Fred’s building on Getwell Road in Memphis. The filing comes as debate continues over a potential vote to pause data center development in the city.

announcementmoratorium

FiveC Group has filed a permit for a $575 million data center project at the former Fred’s building on Getwell Road in Memphis. The Ohio-based group had already received approval for earlier steps and is continuing to advance the project.

The filing comes amid ongoing discussion about a possible pause on data center development in Memphis. ABC24 anchor Kevin McNamara reported that the potential vote has not stopped the Getwell Road project from moving forward.