Oregon Approves Rule Requiring New Large Data Centers to Pay Full Electricity Costs

Oregon Approves Rule Requiring New Large Data Centers to Pay Full Electricity Costs

News ClipKDRV·OR·11/13/2026

The Oregon Public Utility Commission approved a rule requiring new data centers using at least 20 megawatts in Pacific Power's Oregon service area to pay the full cost of their electricity service. The rule requires long-term service agreements and direct payment for needed electric infrastructure, rather than shifting those costs to other customers.

electricitygovernmentannouncement
Gov: Oregon Public Utility Commission

The Oregon Public Utility Commission approved a framework placing new data centers that consume 20 megawatts or more into a separate Pacific Power customer class. Under the rule, the facilities must cover the full cost of their electricity service, sign long-term agreements and pay for infrastructure required to serve them.

The policy resulted from an agreement involving Pacific Power, commission staff, the Oregon Citizen's Utility Board and the Green Energy Institute, and implements Oregon's 2025 POWER Act. Pacific Power senior vice president Rick Link said the approach is intended to support data center investment while protecting affordability for existing customers.