Quincy data center growth faces power limits, eminent domain fight over new transmission line
Quincy's data center expansion has brought major tax revenue, jobs and infrastructure improvements, but Grant County Public Utility District has capped new data center construction because of limited electricity. A planned transmission line from Wanapum Dam to Quincy would cross nearly 40 private properties, prompting landowners to challenge eminent-domain acquisitions; a judge has allowed the process to move forward while leaving compensation disputes unresolved.
Quincy, Washington, has become one of the nation’s early data center hubs since Microsoft opened its first facility there about 20 years ago. Seven other companies have since built facilities, helping fund a fire station, hospital, schools and other public improvements. Quincy School District Superintendent Nick Bergman said data center tax revenue has paid for more than half of the district’s facilities and helped lower property taxes. Microsoft expects roughly 700 data center employees in Quincy by the end of the year, along with additional security workers and related electrical-contracting jobs.
The growth has also strained the community’s electricity and water supplies. Grant County Public Utility District has limited new data center development until additional power is available, citing pressure from energy-intensive artificial intelligence services. A proposed transmission line from Wanapum Dam to Quincy would cross nearly 40 private properties, and affected owners say the selected route was more damaging and expensive than alternatives using public land. A judge ruled that the eminent-domain process could proceed but did not determine whether the utility offered adequate compensation. Microsoft also says the area’s data centers use roughly as much water as 32,000 people and has helped build water-treatment facilities to address demand.