New Braunfels Data Center Rules: Setbacks, Aquifer Ban

New Braunfels Data Center Rules: Setbacks, Aquifer Ban

News ClipHoodline·New Braunfels, Comal County, TX·10/21/2026

New Braunfels officials are considering stricter data center rules, including 500-foot setbacks from homes, a ban in the Edwards Aquifer recharge zone, mandatory special-use permits, noise limits and closed-loop cooling. The city has scheduled a Planning Commission hearing and City Council vote, while a proposed moratorium and a nearby CloudBurst Texas project add urgency to the debate.

zoningoppositionenvironmentalgovernmentelectricitywatermoratorium
Gov: City of New Braunfels, New Braunfels Planning Commission, New Braunfels City Council, Guadalupe County Commissioners Court, Texas Commission on Environmental Quality, Electric Reliability Council of Texas, Office of the Texas Governor, Office of the Attorney General of Texas, Texas Governor Greg Abbott, Texas Attorney General Ken Paxton

New Braunfels is drafting an ordinance that would limit data centers to heavy-industrial zones, require City Council special-use permits, impose 500-foot residential setbacks and a 55-decibel noise limit, and prohibit facilities over the Edwards Aquifer recharge zone. Developers would also need to use closed-loop cooling and obtain proof that local electric and water infrastructure can support their projects.

The New Braunfels Planning Commission is scheduled to hold a public hearing Nov. 4, followed by a City Council first reading Nov. 9. Mayor Michael French requested the council discussion, and a data center moratorium has also been proposed. The regulatory effort follows a pre-development request for a proposed facility along FM 1101 and broader concerns about noise, water use and grid capacity.

Nearby, Guadalupe County commissioners voted 3-2 to reject a proposed $500 million property-tax abatement for CloudBurst Texas LLC's planned campus on Francis Harris Lane, citing incomplete environmental information and limited county land-use authority. State officials have separately scrutinized data center permitting, grid interconnection demand and water-use reporting across Texas.