St. Joseph County board approves sound wall around Microsoft data center
The St. Joseph County Board of Zoning Appeals voted 5-1 to approve a 30-foot sound wall near Microsoft's data center campus in Granger. Microsoft says the wall could reduce noise by up to 16 decibels, while residents raised concerns about noise and other impacts, including whether the wall could redirect toll-road noise toward the neighborhood.
The St. Joseph County Board of Zoning Appeals approved Microsoft's proposed 30-foot sound wall near its data center campus in Granger by a 5-1 vote. The wall will run along the Indiana Toll Road next to the campus, and Microsoft said it could reduce noise by as much as 16 decibels.
Residents have raised concerns about persistent noise and other effects associated with the project. Board members questioned the wall's materials and whether it could reflect toll-road noise back toward nearby neighborhoods, but those questions remained unanswered before the vote. Angela Smith presented the site plan during the public hearing.