300 Jones Road AI data center plan rejected by Spartanburg Co.

News Clip2:28WSPA 7News·Spartanburg County, SC·8/26/2026

Spartanburg County's Board of Zoning Appeals unanimously rejected a data center plan at 300 Jones Road for the second time, upholding staff's denial due to application deficiencies. Residents expressed strong opposition, while developers argued they had invested heavily and the county changed its stance after a moratorium was proposed.

zoningoppositionmoratoriumgovernment
Gov: Spartanburg County, Board of Zoning Appeals, County Planning Commission, County Council

The Spartanburg County Board of Zoning Appeals unanimously rejected plans for an AI data center at 300 Jones Road for the second time. The decision upheld the staff's initial denial, citing deficiencies in the developer's application. Local residents, who have actively opposed the project, applauded the board's decision, expressing gratitude that their community's interests were upheld.

The data center developers argued against the denial, stating they had invested over $28 million into the project based on prior county indications that a data center could be built. They contended that new grounds for denial, such as a recently proposed moratorium by the County Council, should not be considered for their previously submitted application. However, county staff maintained that the initial denial was final and any new submission would be considered a new application, which would then be subject to the moratorium first read by the County Council on June 22. Representatives for White House Data Centers declined to comment on the ruling.